The First Question Bluffdale Homeowners Ask After Cost
Once homeowners in Bluffdale, Utah decide they want to build a custom home, the very next question is almost always:
“How long does it take to build a custom home from start to finish?”
The short answer is: longer than most people expect—but for good reasons.
A realistic custom home timeline in Utah is typically 8 to 14 months, depending on design complexity, permitting, lot conditions, and finish level.
This guide breaks down each phase of the custom home building process, explains how long it usually takes in Bluffdale, and shows you where delays most often happen—so you can plan with clarity instead of frustration.
Quick Answer: Average Custom Home Timeline in Utah
For most Bluffdale custom homes:
- Design & planning: 1–3 months
- Permits & approvals: 1–3 months
- Construction: 6–10 months
Total time: 8–14 months from start to finish
Some homes move faster. Others take longer. Understanding why helps set realistic expectations.
Why Custom Homes Take Longer Than Most People Expect
Custom homes are not production homes. Nothing is pre-built, pre-approved, or mass-scheduled.
In Bluffdale, timelines are influenced by:
- City and Salt Lake County permitting
- Engineering requirements
- Lot grading and soil conditions
- Weather (especially winter excavation)
- Trade availability
- Material lead times
Time is the trade-off for customization, quality, and long-term value.
Phase 1: Design, Planning, and Budgeting (1–3 Months)
This phase happens before any dirt is moved, but it’s one of the most important.
What happens during this phase:
- Initial consultation and goal setting
- Budget alignment
- Floor plan design
- Elevations and exterior design
- Engineering input
- Energy-efficiency planning
In Bluffdale, many homeowners choose:
- Larger floor plans
- Finished basements
- Open-concept layouts
- High-efficiency systems
Rushing design almost always adds months later through redesigns and change orders.
Phase 2: Permits, Engineering, and City Approval (1–3 Months)
Permitting timelines are one of the biggest variables in Utah custom home construction.
This phase includes:
- Structural engineering
- Energy compliance documentation
- City plan review
- Salt Lake County approvals
- Utility coordination
Bluffdale permitting timelines can vary based on:
- Complexity of the design
- Volume of applications
- Revisions requested by the city
Permits cannot be rushed—and skipping them creates major resale and insurance problems.
Phase 4: Framing and Structural Build-Out (1–2 Months)
This is when the home finally starts to look like a house.
Work completed in this phase:
- Framing walls, floors, and roof
- Sheathing
- Windows and exterior doors
- Roofing
- Weatherproofing
Once framing is complete, inspections are required before moving forward.
Phase 5: Mechanical Rough-Ins (1–2 Months)
This phase includes:
- Electrical wiring
- Plumbing lines
- HVAC ductwork
- Low-voltage systems
Everything installed here must pass inspection before walls can be closed.
Mechanical rough-ins are a common bottleneck because multiple trades must coordinate perfectly.
Phase 6: Insulation, Drywall, and Interior Prep (1–2 Months)
At this stage, the home starts to feel finished inside.
This phase includes:
- Insulation installation
- Drywall hanging and finishing
- Primer coats
- Interior inspections
Weather and humidity can affect drywall curing times, especially in colder months.
Phase 7: Interior Finishes and Final Details (2–3 Months)
This is the longest and most detailed phase.
Includes:
- Cabinet installation
- Countertops
- Flooring
- Trim and doors
- Painting
- Tile work
- Appliance installation
- Lighting and fixtures
Custom finishes take time—and rushing this phase often leads to regret.
Phase 8: Final Inspections and Move-In (2–4 Weeks)
Before occupancy:
- Final inspections are completed
- Punch-list items are addressed
- Certificate of occupancy is issued
Only after this can you officially move in.
What Causes Custom Home Delays in Bluffdale?
Common causes include:
- Design changes mid-build
- Permit review delays
- Weather impacts
- Material backorders
- Trade scheduling conflicts
Most delays are avoidable with proper planning and realistic expectations.
How to Keep Your Custom Home on Schedule
1. Finalize design early
2. Make finish selections before construction
3. Avoid changes once framing begins
4. Work with an experienced design-build team
5. Plan for weather and inspections
Final Answer: How Long Does It Take to Build a Custom Home in Utah?
Most custom homes take 8–14 months from initial planning to move-in.
The more complex the design and finishes, the closer you’ll be to the longer end of that range.

Plan Your Timeline the Right Way
If you’re considering building a custom home in Bluffdale, guessing timelines can create unnecessary stress.
A professional plan gives you clarity from day one.
Schedule a Free Custom Home Timeline Consultation
Visit https://basementfinishing.com/our-services/custom-homes/
Call 801-733-7070
Basements Etc helps Bluffdale homeowners understand realistic timelines, avoid delays, and build with confidence.
Frequently Asked Questions (FAQ)
Can a custom home be built in under 6 months?
Rarely. Only very simple builds with minimal customization move that fast.
What phase takes the longest?
Interior finishes and inspections typically take the most time.
Does winter slow construction in Utah?
Yes, especially excavation and concrete work.
Can I speed up the process?
You can reduce delays by finalizing decisions early—but you can’t bypass permits or inspections.
Is the timeline worth it?
For most homeowners, yes. Custom homes are built for long-term living, not speed.